Title: BARRIE PERFORMING ARTS CENTRE - DESIGN DEVELOPMENT ADVANCEMENT 1. That the results of the 50% Design Development phase and the Class C cost estimate for the Barrie Performing Arts Centre (PAC), as presented in Staff Report FAC007-25, be received. 2. That staff in the Corporate Facilities Department proceed with the Barrie Performing Arts Centre project as set out in Staff Report FAC007-25 and as detailed in the design documents prepared by Hariri Pontarini Architects (HPA), attached as Appendix A to Staff Report FAC007-25. 3. That a Gala Seating System be included in the project design scope and that the total requested project budget be increased by $10M to $85M. 4. That capital project, EN1629 - Performing Arts Centre Park, be removed from the 10-year Capital Plan with funding of $2.8M from the Tax Capital Reserve being reallocated to the Performing Arts Centre project. 5. That staff award a single-source contract to Hariri Pontarini Architects (HPA) for the provision of ful...
Attachments: 1. FAC007-25.pdf, 2. Appendix A - PAC Design Development Package
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

BARRIE PERFORMING ARTS CENTRE - DESIGN DEVELOPMENT ADVANCEMENT

 

1.                     That the results of the 50% Design Development phase and the Class C cost estimate for the Barrie Performing Arts Centre (PAC), as presented in Staff Report FAC007-25, be received.

 

2.                     That staff in the Corporate Facilities Department proceed with the Barrie Performing Arts Centre project as set out in Staff Report FAC007-25 and as detailed in the design documents prepared by Hariri Pontarini Architects (HPA), attached as Appendix A to Staff Report FAC007-25.

 

3.                     That a Gala Seating System be included in the project design scope and that the total requested project budget be increased by $10M to $85M.

 

4.                     That capital project, EN1629 - Performing Arts Centre Park, be removed from the 10-year Capital Plan with funding of $2.8M from the Tax Capital Reserve being reallocated to the Performing Arts Centre project.

 

5.                     That staff award a single-source contract to Hariri Pontarini Architects (HPA) for the provision of full professional services for the Barrie Performing Arts Centre, from the current design stage through to construction completion, in accordance with the City’s non-standard procurement process, as outlined in Staff Report FAC007-25. (FAC007-25) (P29/25)