File #: ENG001-110110    Version: 1 Name:
Type: Staff Report Status: Carried
File created: 1/10/2011 In control: Engineering Department
On agenda: 1/10/2011 Final action: 1/10/2011
Title:
Attachments: 1. ENG001-110110.pdf
Related files: 15-G-261, TMP-15502, 16-A-003, 16-G-003
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

The city of STAFF REPORT ENGOOI-Il

Page: 1

January 10, 2011

File: A19-2N

TO: GENERAL COMMITTEE

SUBJECT: SUNNIDALE PARK RESERVOIR AND BOOSTER PUMPING STATION

DESIGN ENDORSEMENT BY COUNCIL

PREPARED BY AND G. KING, P. Eng, PMP %'L

KEY CONTACT: SENIOR PROJECT ENGINEER - ENVIRONMENTAL (Ext. 4532)

SUBMITTED BY: R. W. MCARTHUR, P. Eng.

/2

24'

DIRECTOR OF ENGINEERING

GENERAL MANAGER R. J. FORWARD, MBA, M.Sc., P. Eng.

APPROVAL: GENERALMANAGEROFINFRASTRUCTU VEL PMEJET,8CULTURE

/ /1'

CHIEF ADMINISTRATIVE JON M. BABULIC /

OFFICER APPROVAL: CHIEF ADMINISTRATIVE OFFICER / '

RECOMMENDED MOTION

That the Design of the Sunnidale Park Reservoir and Booster Pumping Station be endorsed with

the following changes to the Sunnidale Park Master Plan Appendix F:

a) The Booster Pumping Station dimensions be approximately 9 metres by 17 metres.

b) The location of the Reservoir be moved approximately 10 metres westerly and 3.5 metres

northerly, while not decreasing the offset from the Sunnidale Road right-of-way so that an

additional 20 trees can be saved and the height of the north-east corner of the reservoir

reduced.

2. That any minor modifications to the design be reviewed with the "Friends of Sunnidale"

consultation group and outlined via Memorandum to General Committee prior to tender and

construction.

PURPOSE & BACKGROUND

3. The design of the Sunnidale Park Reservoir and Booster Pumping Station has been well

advanced including the enhanced public participation component.

4. The purpose of this Staff Report is to:

a) Advise General Committee of the progress of the Design

b) Advise General Committee that amendments to the Sunnidale Park Master Plan will be

required as the Sunnidale Park Reservoir and Booster Pumping Station design has

progressed.

Council Motion 06-G-500, as amended by Resolution 04-A-450 (Amendment #1), directed Staff to

undertake the site selection/design concurrently with the preparation of the Sunnidale Park

Master Plan. Further, Motion 06-G-501, as amended by Resolution 04-A-450 (Amendment #2)

directed that a Sunnidale Park Master Plan Steering Committee be struck and also directed the

composition of said committee. Both Motions are included in Appendix 'A".The Gity of STAFF REPORT ENGOOI -11

Page: 2

B!JE

January 10, 2011

Pending#

6. Council Motion 09-G-262 (See Appendix A") adopted the Sunnidale Park Master Plan in principle

which thus determined the site location of the Sunnidale Reservoir and Booster Pumping Station.

(A copy of the Plan is provided in the Councillor's Lounge and the 4th Floor City Hall Engineering)

7. Note that further to the Sunnidale Master Plan, Council Motion 09-G-267 (See Appendix "A")

directs staff to present the final detail design drawings to Council for endorsement.

8. Council Motion 09-G-315 (See Appendix "A") directed staff to issue the Municipal Class

Environmental Assessment (EA) Notice of Completion which identified the need for a Reservoir

and Booster Pumping Station, and also confirmed that Sunnidale Park as the preferred area. The

Notice of Completion was issued July 23, 2009. In addition, staff were to report back to General

Committee with the preliminary design for endorsement. (A copy of the Class EA document is

provided in the Councillors' Lounge and the 4th Floor City Hall - Engineering).

9. A Project Milestone History is provided in Appendix "B" that summarizes the key milestones to

date.

10. Note that while outside the scope of this Staff Report, the Design and Construction Branch of the

Engineering Department is project managing several Transmission Watermain projects that are to

be constructed in conjunction with bringing the Sunnidale Park Reservoir and Booster Pumping

Station on-line that include as follows (Note that the "Proposed" components are required for the

integration of the Sunnidale Park Reservoir and Booster Pumping Station into the overall water

distribution system, however they are still subject to the current Work Planning exercise):

a) Anne Street/Letitia Street Transmission Watermain from Anne Street Booster Pumping

Station/Reservoir to Sunnidale Road (Construction completed 2009)

b) Anne - Cundles Transmission Watermain from the Anne Street Reservoir to the Bayfield

Street Elevated Water Storage Reservoir (Completed 2010)

c) Sunnidale Road Transmission Watermain from Letitia Street to Wellington Street

including an undercrossing of Highway 400 (Proposed design in 2010/2011, Proposed

construction 2012)

d) Sunnidale Road Transmission Watermain from Letitia Street to Sunnidale Park

Reservoir/Booster Pumping Station (Proposed design in 2011, Proposed construction

2012)

e) Sunnidale Road Transmission Watermain from Sunnidale Park Reservoir/Booster

Pumping Station to Cundles (Proposed design 2011, Proposed construction 2012).

11. General Committee was advised that a public Open House was to be held on June 29, 2010.

The objective of the Open House was to consult with the public regarding the Preliminary Design

Concepts, including:

a) Present architectural options

b) Present landscaping treatment

c) Present design layout

d) General follow-up on project process. The City of STAFF REPORT EN000I-11

Page: 3

IB'E

January 10, 2011

12. The June 29, 2010 Open House was well attended, with 57 attendees. The Open House was

advertised in the local papers, included in the City Page, radio advertisements, hand-delivered

notifications to those residents that had previously expressed interest in the project, and a handdelivered notice to the residents in the general area.

13. Subsequently, the June 29, 2010 Open House presentation boards were placed on the City's

website. They can still be found on the project webpage at www.barrie.ca/Parks and Trails >

Parks > Sunnidale Park!

14. In conjunction with the June 29, 2010 Open House, those who were interested could participate

in a survey, or on line, at the above noted web address (note that the survey has since been

made inactive since the official public comment period submission date has expired). The results

of the survey will be discussed in the Analysis section of this Staff Report.

Sunniclale Park Master Plan

15. Section 4.4.1 of the Sunnidale Park Master Plan, specifically Table 1.0 Park Program, identifies

various Program Elements for each Amenity/Facility. For the Water Reservoir and Pump House

the Program Elements are shown in Appendix "C" and how they have been satisfactory

addressed in the Detail Design.

16. Section 6.2 of the Sunnidale Park Master Plan, specifically Table 2.0, identifies the

Implementation Strategy. A summary of the pertinent recommendations are included in Appendix

"C", and how they have been, or will be, satisfactorily addressed in the Detail Design.

17. As per Motion 10-G-201 (See Appendix A), on November 17, 2010 The Friends of Sunnidale

Park Consultation Group were presented an update of the project and were shown the Design

Drawings. The presentation was well received and there were no comments that would have

changed the design.

Approvals/Sign-offs

18. As part of the Preliminary Design various stakeholders were circulated information, including

Approval Agencies, Utilities and City of Barrie Departments. A summary is provided in Appendix

"D" of the Approvals/Sign-offs that will be required.

Class EA Commitments

19. Appendix "E" summarizes the Class EA commitments and associated commitments and explains

how each commitment has been addressed.

Preliminary Design

20. A Preliminary Design Report has been prepared by the Engineering consultants, Cole

Engineering, entitled Sunnidale Park Reservoir and Booster Pumping Station, Preliminary Design

Report, dated November 2010 that summarizes the criteria that the detail design will be

developed with, based on technical requirements and public input. (A copy of which is provided in

the Councillors' Lounge and the Floor City Hall - Engineering)

21. In general, the design of the Sunnidale Park Reservoir and Booster Pumping Station is comprised

of:

a)

b)

18.4 million litre underground reservoir (dimensions approximately 40 m by 20 m)

15 million litres per day - Booster Pumping

17 m) that contains pumps, standby power,

electrical, mechanical, and instrumentation

Station (dimensions approximately 9 m by

chlorination equipment, process pipework,

c) Earthworks, Restoration and Landscaping.The City of STAFF REPORT ENGOOI-Il

Page:4

January 10, 2011 edM

22. Several design drawings have been provided (See Appendix "F') in the Councillors' Lounge and

the

4th

Floor City Hall - Engineering. The design drawings are approximately at the 50% stage,

which means the remaining design is the detailing of structural reinforcement/connections, interior

electrical detailing, process piping, instrumentation, etc. It is not anticipated that there will be any

major redesigns or reworks at this stage of the design.

Architectural

23. The exterior architecture is shown in Appendix "F".

24. The internal equipment layout of the proposed pumping station has been consolidated to

minimize the above grade footprint. Below grade, there is an equivalent of two stories that are

required to accommodate the associated pipework. The Booster Pumping Station's simple

rectangular form is enhanced by the curving roof form that provides screening of roof mounted

equipment and sheltering overhangs on the north and south sides. The curved roof structure was

chosen to reduce the apparent height of the Booster Pumping Station. The proposed roofing

material is a durable, long life, prefinished metal standing seam system.

25. The Booster Pumping Station's exterior will have a natural stone masonry base, with a

combination of cementious panels and wood siding on the upper panels. The exposed structure

and soffits will have a wood finish. High level glazing will be introduced on the north façade and a

glazed section of roof will allow infiltration of natural light to the windows.

26. Exterior material colours have been selected to blend with the natural tones of the coniferous

background, including the metal roofing.

27. To reduce the building maintenance due to the potential of vandalism, the natural stone base,

which is proven tough and durable, has been used and windows have been placed high in the

structure. A balance was sought since too much stone would make the building appear bigger

and stronger instead of trying to blend into the background.

28. The interior of the building will be painted concrete block, with specialized sound absorbing

boards in the stand-by generator room, including a "Hospital Grade-plus" silencer and deep

acoustical louvres. The height of the stand-by generator exhaust stack has been nearly

eliminated by utilizing specialized equipment that will be located within the framing of the curved

roof, without increasing the building's overall height.

29. The Booster Pumping Station's overall height has been minimized as much as possible. Several

strategies were investigated but ruled out, such as: placing the taller equipment below ground

(however, more susceptible to flooding equipment damage); and using smaller equipment and

omitting equipment (however, caused Health and Safety issues if chlorine scrubber was omitted).

It was concluded that the height of the building is dependent upon the height of the chlorine

scrubber and the stand-by generator, specifically in combination with a silencer. Several

renditions and discussions with the designers have reduced the height of the roof; however, the

current height is required to accommodate the equipment. The architect proposed several

options to minimize the roof height while still maintaining functionality. To eliminate the attic

space, a flat roof could be used; however there would still be screening requirements for the

Heating and Ventilation equipment. The option of a curved roof was proposed which would

reduce the overall height that would have resulted from a peaked roof. The curved roof provides

additional architectural flexibility with overhangs, etc. The roof configuration options were

presented at the Public Open House and the results are provided in the below Analysis Section.

30. PowerStream is currently studying the power supply requirements to the Sunnidale Park Booster

Pumping Station. Preliminary indications are that a supplementary overhead power line will be

required within the existing Sunnidale Road Right-of-Way from Cundles Road to the Booster

Pumping Station site. It is anticipated that the existing poles will be replaced with taller poles but

will be in the approximate same locations. There will then be a green transformer required at the The City of STAFF REPORT ENGOOI-Il

Page: 5

B1J1E

January 10, 2011

east edge of the Sunnidale Road right of way prior to bringing the power underground to the

Booster Pumping Station Building. PowerStream has advised that due to the taller poles there

may be a need to trim the trees at the higher levels. Also, PowerStream noted there may be a

short power interruption to transfer to the new powerline in 2011. PowerStream will use their

typical notification process to advise their customers of the temporary interruption.

Landscaping

31. The landscape development (refer to architectural drawings in Appendix "F") will consist of

preserving existing vegetation where possible and replacement or new landscaping in keeping

with the Sunnidale Park Master Plan. After detail review and on consultation with the City's urban

forester, the reservoir siting was nominally adjusted to preserve the largest number of the highest

quality existing vegetation. There will also be infilling of the existing coniferous edge along

Sunnidale Road to provide additional screening. The planting work will take place in Fall 2010 or

early Spring 2011 so that the screening will be in place prior to construction.

32. One of the key recommendations in the Sunnidale Park Master Plan was to minimize the

reservoir impacts on the park. During the design development of the building and its placement

within the park, the view shed from Sunnidale Road will be maintained.

33. Prior to construction of the reservoir, existing fescue grasses and topsoil found presently within

the construction limit will be saved as "Seed Bank" material, and used in the restoration of the

reservoir footprint and areas disturbed during construction. Gentle berms and an undulating

landscape will reflect the former golf course topography and character of the park. As a result,

fencing will not be required around the structure, further integrating this infrastructure into the

natural character of the park.

34. A meandering pathway will cross the reservoir area, with small seating areas incorporating

benches, stone and ornamental grass features, which is reflective of the park arboretum site.

35. Proposed vehicle circulation routes will be minimized with existing internal park accesses utilized

where possible. Only the routes needed for daily access will have asphalt. Other routes will have

a reinforced grass type surface and/or will be made part of the trail system.

ANALYSIS

36. Feedback on the preliminary design was obtained from the June 29, 2010 Open House

questionnaires/survey; electronic survey; individual responses; and individual meetings.

37. The survey results are included in Appendix "G". In general the participants responded as follows:

a) 86% preferred the curved roofline option, over the flat roof

b) 98% agreed with the use of natural building materials

c) 96% agreed that the building should blend into the background

d) 79% agreed that the appropriate level of architecture has been included in the design

e) 83% agreed that the proposed location has kept the view shed intact

f) 96% agreed with the conceptual landscaping plan

g) 90% agreed that the information that was available was satisfactory to assist in providing

response.38. As part of the survey results, written comments from the participants are summarized in Appendix

"G". Responses by City Staff are also included as part of the aforementioned summary.

39. As Preliminary Design progressed, it was evident that there would be two main issues to be

addressed:

a) In the Sunnidale Park Master Plan the approximate area for the inground reservoir was

(90 m by 35 m) which is comparable to the current reservoir sizing (91 m by 38.5 m).

However, the functionality of the Booster Pumping Station would require a larger footprint

than what was stated in the Park Master Plan document which stated an approximate

area of 80 m2 (8 m by 10 m) whereas the current design requires 153 m2 (9 m by 17 m).

The reasons for the floor sizing are as follows:

i) It was found that since the reservoir floor level was lower than typical, that

additional floor area was required for lifting access and a staging area to lift

equipment from three floors down.

ii) It was also deemed prudent to add an emergency chlorine scrubber system due

to the proximity of the park. A scrubber has typically not been provided in the

past at other water facilities due to the minimal probability of an accidental

interior leak.

iii) An additional pump was added to increase security and robustness of the overall

water system.

The table below shows comparable City Booster Pumping Stations. It can be seen that

the proposed Preliminary design of the Sunnidale Road Booster Pumping Station has a

reasonable footprint.

WATER FACILITY AREA (FOOTPRINT)

Identified in the Sunnidale Park Master Plan -Proposed

Booster Pumping Station sizing

80 m2 (8 m by 10 m)

Proposed Preliminary Design - Sunnidale Park Booster

Pumping Station (includes chlorine scrubber)

153 m2 (9 m by 17 m)

Existing Big Bay Point Road Booster Pump Station 144 m2 (8 m by 18 m)

Existing Harvie Road Booster Pumping Station 198 m2 (11 m by 18 m)

b) The second main issue relates to the siting of the reservoir as proposed in the Sunnidale

Park Master Plan - Figure F Master Plan. When the outline for the conceptual reservoir

was overlain on a detailed tree Inventory, it was found that if the reservoir was shifted

westerly approximately 10 m and 3.5 m northerly, that the overall quantity of trees that

would be impacted was reduced. The proposed shift also saved a healthy White Pine

(500 mm diameter trunk with a 10 m canopy). The City's Urban Forester and the

Supervisor of Parks Planning have concurred that the proposed shift will be better for the

preservation of the existing vegetation. An additional benefit of shifting the reservoir is

that the ground elevation of the north-east corner will be lower by an additional estimated

300 mm. 41. The Architectural/Engineering/Landscaping Drawings and Contract Documents will be quality

checked for completeness and accuracy by City staff.

42. A comprehensive and thorough geotechnical, existing subsurface utilities and archaeological

investigations have been undertaken at key locations. Recommendations from the various

background reports have been checked to ensure they have been incorporated into the drawings.

43. Approval agencies preliminary comments have been received and their effects on the scope of

work and budget have been assessed and incorporated into the overall budget.

44. Project cost forecasting and budgeting have taken into account the possibility of unexpected

increased construction costs by establishing contingencies that reflect the project type and

corn plexity.

45. Subject to Council approval of the recommended motion, Staff will finalize the detail design

drawings. Any minor modifications to the design will be reviewed with the "Friends of Sunnidale"

consultation group and outlined via Memorandum to General Committee prior to proceeding to

tender and construction.

46. Staff will enter into agreements with specialty consultants/contractors (for example, biologist,

roofing inspection) as required, subject to budget limitations and procurement policies.

ENVIRONMENTAL MATTERS

47. The following environmental matters have been considered in the development of the

recommendation:

a) In accordance with the City's Energy Conservation Policy, the Sunnidale Park Reservoir

and Booster Pumping Station have been designed with energy conservation in mind.

Due to the unique type of building, it is challenging to implement typical LEED

(Leadership in Environmental and Energy Design) Silver measures therefore the project

will meet the intent of LEED where practical and cost effective. The City's Environmental

Officer has provided his endorsement of the preliminary design.

b) Typical construction techniques will be utilized to minimize sediment and erosion

originating from the construction site.

c) Tree protection will be in place prior to construction commencement.

ALTERNATIVES

48. The following Alternatives are available for consideration by General Committee:

Alternative #1 General Committee could choose to not endorse the design and require

the Consultant to redesign the Booster Pumping Station.

This Alternative is not recommended as the public survey results show

that the appropriate level of architecture has been utilized and the curved

roof is the preferred design.The City of STAFF REPORT ENGOOI-Il

Page: 8

January 10, 2011

Alternative #2 General Committee could choose to have the final detail design drawings

presented to Council for endorsement prior to going to tender and

construction.

This Alternative is not recommended because key design elements of

public concern have been established and are ready to be endorsed.

Any minor modifications to the design can be reviewed with the "Friends

of Sunnidale" consultation group and outlined via Memorandum to

General Committee.

FINANCIAL

49. There are no direct financial implications related to the recommendations in this report as it

relates to the endorsement of the design.

50. Construction is anticipated to begin in the Fall of 2011, subject to the approval of funding as part

of the 2011-2020 Business Plan. The construction and clean-up is anticipated to be completed in

the Spring of 2013. The draft 2011 - 2020 Business Plan shows the following construction and

engineering cash flow with funding from the water rate reserve fund and development charges:

2011 - $ 3.OM

2012 - $15.8M

2013 - $ 1.OM

2014 - $ .4M (maintenance)

The recommended design had no impact on previous budget projections ($21 .OM in 2009).

51. It is anticipated that the impact on the operating budget would be $80,000 (2010 dollars) starting

in 2013. The operating impact would include utilities, chemicals, building maintenance, staff time

and equipment.

LINKAGE TO COUNCIL STRATEGIC PRIORITIES

52. The recommendations included in this Staff Report support the following City Council's Strategic

Priorities:

E1 Attract, Retain and Expand Business for Barrie

E1 Ensure Proactive Communications with the public and increased

opportunities for Citizen Engagement

E1 Increase fiscal responsibility to ensure controlled spending and best value for

tax dollars The City of STAFF REPORT ENGOOI -11

Page: 9

IBJE

January 10, 2011

APPENDIX "A"

The City of City Clerk's Office

B1JE

COUNCIL DIRECTION MEMORANDUM

TO: Director of Engineering

Director of Leisure, Transit & Facilities

Director of Operations

City Treasurer

FROM: John Sisson, City Clerk

DATE APPROVED

BY COUNCIL: October 2, 2006

AMENDED BY RESOLUTION 04-A-450:

AMENDMENT #1

That motion 06-G-500 of General Committee Report No. 37, Section "G" concerning the

Proposed Zone 2 North System Improvements Municipal Class Environmental

Assessment Schedule "B" Document be removed from Section "G" and reintroduced as

Section "H".

06-G-500 PROPOSED ZONE 2 NORTH SYSTEM IMPROVEMENTS MUNICIPAL CLASS

ENVIRONMENTAL ASSESSMENT SCHEDULE "B" DOCUMENT

That Council consideration of the following motion be deferred until the City Council

meeting scheduled for October 2, 2006:

"That, further to the direction provided in motion 06-G-444 regarding the Proposed Zone 2

North System Improvements Municipal Class Environmental Assessment Schedule "B"

Document, the final site selection/project design for the construction of a water reservoir

located within Sunnidale Park be undertaken concurrently with the completion of a Parks

Master Plan for Sunnidale Park including the adjacent Environmental Protection (EP)

Area." (File: D00) (06-G-444) (ENGO45-06)"

Direction:

Director of Engineering - action

Director of Leisure, Transit & Facilities - action

Director of Operations - note

City Treasurer - note

ThE crr

OCT 1P2006

THE CITY OF BARRIE

[EERlNG DEPARTMENT

I INITIAL

DIREGTOR

•/"

MON OF

MON OFT1

_________

NOR 0TI)

OTHER_____

---____

V

_____

FILETThe City of

BAJ E

STAFF REPORT ENGOOI-11

Page: 10

January 10, 2011

File: A19-2N

Pending #:

FROM:

DATE APPROVED

BY COUNCIL:

John Sisson, City Clerk

October 2, 2006

AMENDED BY RESOLUTION 04-A-450:

AMENDMENT #2

That motion 06-G-501 of General Committee Report No. 37, Section "G" concerning

Sunnidale Park Master Plan Steering Committee be removed from Section 'G" and

reintroduced as Section "I".

06-G501 SUNNIDALE PARK MASTER PLAN STEERING COMMITTEE

That Council consideration of the following motion be deferred until the City Council

meeting scheduled for October 2, 2006:

That a Sunnidale Park Master Plan steering committee reporting through the

Community Services Committee, be struck to help oversee the preparation of a

comprehensive Parks Master Plan for Sunnidale Park including the adjacent

Environmental Protection (EP) Area.

2. That the Steering Committee be comprised of two (2) members of council (one of

which is the Ward Councillor), one (1) representative of the Barrie Garden Club

and two (2) members of the public to be appointed through Striking Committee

and that the Staff Report to Striking Committee include recommended terms of

reference for the Sunnidale Park Master Plan Steering Committee.

3. That a Request for Proposals be issued for the development of a Master Plan for

Sunnidale Park." (File: COO) (06-CMSC-041)

Direction:

City Clerk - Nina - note for CMSC

- Charlene - note for Striking Committee

Director of Engineering - action

Director of Leisure, Transit & Facilities - action

Director of Operations - note

OCT \ i 2OQ

E4GINEERlNG

.,h.

NrflAL;

MSRO

OiFiE

PLE r The Gity of

BA E

STAFF REPORT ENGOOI-Il

Page: 11

January 10, 2011

File: A19-2N

Pending #:

The City of City Clerk's Office

BiR13JE

COUNCIL DIRECTION MEMORANDUM

TO: Director of Planning

Director of Engineering

FROM: Dawn McAlpine, City Clerk

DATE APPROVED

BY COUNCIL: June 8, 2009

09-0-262 SUNNIDALE PARK MASTER PLAN

That the Sunnidale Park Master Plan be adopted in principle. (06-0-500) (06-0-501) (060-578) (09.0-023) (09-G-021) (09-0-184) (09-CMSC-038) (File: R00)

Direction:

Director of Engineering - note

Director of Planning - note

L4

•JLUO

I

THE C7 OF EARRlE

lNEE0 oT1ENLJ

THE CITY OF BARRIET

ENGINEERING DEPARTMENT

ACI1ON INFO NI11AL

MOR OF P&SJ

JL I

OTHER

&LLIJ .-'

1/u

L i±.

ALE#The City of

BA E

STAFF REPORT ENGOOI-Il

Page: 12

January 10, 2011

File: A19-2N

Pending #:

The Ciiy of City Clerk's Office

BABI34E

COUNCIL DIRECTION MEMORANDUM

TO: Director of Planning

Director of Engineering

FROM: Dawn McAJpine, City Clerk

DATE APPROVED

BY COUNCIL: June 8, 2009

09-G-267 SLJNN1DALE PARK MASTER PLAN - FINAL DESIGN DRAWINGS FOR RESERVOIR

That final detail design drawings for the reservoir be presented to Council for

endorsement. (06-G-500) (06-G-501) (06-G-578) (09-G-023) (09G-021) (09-G-1 84) (09CMSC-038) (File: R00)

Direction:

Director of Planning - note

Director of Engineering - action

• 11WOFBARR

ENGINEERING DEPARTMENT

ACI1ON l4FO iNITIAl

VI

1MRL/i

1 JUN 15 2609

I

I THE ClI O BARRIE

I

GIEERIN1\RT1EIT

FiLE # The City of STAFF REPORT ENGOOI-Il

Page: 13

IB!E

January 10, 2011

Pending#

The City of City Clerk's Office

B*TE

COUNCIL DIRECTION MEMORANDUM

FROM: Dawn McAlpine, City Clerk

DATE APPROVED

BY COUNCIL: June 29, 2009

09-G-315 PROPOSED ZONE 2 NORTH WATER SYSTEM IMPROVEMENTS - MUNICIPAL

CLASS ENVIRONMENTAL ASSESSMENT - SCHEDULE "B" DOCUMENT

1. That based on the Municipal Class Environmental Assessment (Class EA) Study,

"Proposed Zone 2 North System Improvements", "Alternative 5B - Provide

Ground Storage/BPS Facility Mutually Shared by Zone 112N; Sunnidale Revised

Site E", as shown in Staff Report ENGOO7-09, be endorsed as the Preferred

Alternative Solution, and that staff file a Notice of Completion with the Ministry of

the Environment.

2. That based on the successful completion of the Class EA process, the

Engineering Department proceed with the preliminary design of the Ground

Storage, Booster Pumping Station and associated watermains, and report back to

General Committee with the design for endorsement. (ENGOO7-09) (File: W032N)

Direction:

Director of Legal Services - note

Director of Engineering- action

Director of Finance - note

THE CITY OF BARRE

ENGINEERI NG DEPARTMENT

0N0iNlTl

DiRECT0 PJ2'wt I4

I0

I,

RIE

______

- '

----IThe City of STAFF REPORT ENGOOI-Il

Page: 14

January 10, 2011

FHe:A19-2N

The City of City Clerk's Office

BIJE

COUNCIL DIRECTION MEMORANDUM

TO: City Clerk

Director of Engineering

Police Chief

FROM: Dawn McAlpine, City Clerk

DATE APPROVED

BY COUNCIL: May 17, 2010

1O-G-201 SUNNIDALE PARK MASTER PLAN CONSULTATION GROUP

1. That a "Friends of Sunnidale Park" consultation group be established to assist

staff and City Council with implementation of the Sunnidale Park Master Plan.

2. That the "Friends of Sunnidale Park" consultation group may include, but not be

limited to the following organizations subject to the park improvements being

proposed:

a) The Barrie Garden Club;

b) Living Green Barrie;

c) The Brereton Field Naturalists Club of Barrie;

d) The four school boards (Simcoe County District School Board, Simcoe

Muskoka Catholic School Board, Conseil Scolaire De District Catholique

Centre-Sud, and Conseil Scolaire De District Du Centre Sud-Ouest);

e) The Barrie Police Services;

f) The First Christian Reformed Church;

g) Ontario Society for the Prevention of Cruelty to Animals (OSPCA Barrie

Branch);

h) Adjacent businesses such as the Travelodge Barrie and Bayfleld Mall;

i) The Lake Sinicoe Region Conservation Authority; and

j) The local service clubs.

3. That public open houses be hosted once per year to provide updates with

respect to the status of the Sunnidale Park Master Plan and obtain feedback

from the general public concerning initiatives related to the Plan.

4. The staff in the Engineering Department be responsible for the overall

coordination of the "Friends of Sunnidale Park" consultation group, and that the

Engineering Department provide annual updates to Council via memorandum on

the implementation of the Sunnidale Park Master Plan and on the

input/recommendations from the public open house, as required. (ENGO31-10)

(File: R04-SU)

Direction:

City Clerk - Dawn/Carey - note

Director of Engineering - action

Police Chief - note The City of

BhR4J E

STAFF REPORT ENGOOI-Il

January 10, 2011

Page: 15

File: A19-2N

Pending #:

APPENDIX "B"

SUNNIDALE PARK RESERVOIR AND BOOSTER PUMP STATION

MILESTONES

June 2005 Municipal Class Environmental Assessment Schedule 'B'

Proposed Zone 2 North System Improvements

o Prepared Environmental Study Report

o Undertook two Public Open Houses (June 2005 and January 2006)

• Update Presentation made to Council (March 2006)

o Site E alternative recommended in Staff Report ENGO45-06 (June 2006)

o Presentation made to Community Services (August 2006)

o ENG 045-06 Staff Report returns to General Committee (October 2006)

Key Motions Associated with Design

o Motion 06-G-500, "That, further to the direction provided in motion 06-G-444

regarding the Proposed Zone 2 North System Improvements Municipal Class

Environmental Assessment Schedule "B" Document, the final site selection/project

design for the construction of a water reseivoir located within Sunnidale Park be

undertaken concurrently with the completion of a Parks Master Plan for Sunnidale

Park including the adjacent Environmental Protection (EP) Area."

• Motion 06-G-501, "That a Sunnidale Park Master Plan steering committee

reporting through the Community Service Committee be struck to help oversee the

preparation of a comprehensive Parks Master Plan for Sunnidale Park including

the adjacent Environmental Protection (EP) area..."

April 2007 Sunnidale Park Master Plan Process

• Established a Steering Committee including members of Council and the public

o Met with stakeholders

o Undertook two Public Information Centres

• Presented the Park Master Plan to General Committee for endorsement, entitled

"Sunnidale Park Master Plan," dated May 2009.

June 2009 Sunnidale Park Master Plan Staff Report

Key Motions Associated with Design

• Motion 09-G-262, "That the Sunnidale Park Master Plan be adopted in principle..."

• Motion 09-G-265, "That a Management Committee (Friends of Sunnidale Park) be

appointed with public representation..."

o Motion 09-G-267, "That final detail design drawings for the reservoir be presented

to Council for endorsement..."The City of

BARN E

STAFF REPORT ENGOOI-Il

January 10, 2011

Page: 16

File: A19-2N

Pending #:

June 2009 Proposed Zone 2 North Water System Improvements

Municipal Class Environmental Assessment - Schedule 'B' Document (ENGOO7-09)

Key Motions Associated with Design

• Motion 09-G-315, "That based on the Municipal Class Environmental Assessment

(Class EA) Study, "Proposed Zone 2 North System Improvements", "Alternative

5B - Provide Ground Storage/BOOSTER PUMPING STATION Facility Mutually

Shared by Zone 1/2N; Sunnidale Revised Site E" as shown in Staff Report

ENGOO7-09, be endorsed as the Preferred Alternative Solution, and that staff file a

Notice of Completion with the Ministiy of Environment."

• Motion 09-G-315, "That based on the successful completion of the Class EA

process, the Engineering Department proceed with the preliminary design of the

Ground Storage, Booster Pump Station and associated watermains and report

back to General Committee with the design for endorsement."

July 2009 Notice of Completion Issued

August Class EA Mandatory Public Comment Period Expired

2009

o No Part Two Orders received by MOE

October Public Request For Proposal Issued

2009

o For the Preliminary Design, Detail Design and Contract Administration

o Cole Engineering awarded project

Public Open House at Dorian Parker Centre

June 29, o Updated Public on design progress

2010

• Reviewed Conceptual designs and alternative roof designs

• Public feedback/survey conducted on conceptual design

November Sunnidale Park Consultation Group

17, 2010 o Staff reviewed the project with the consultation group as per Motion 1 O-G-201

December Design

13, 2010 o With respect to the Class EA, as per Motion 09-G-315, Staff is looking for General

___________ Committee to endorse the design. The City of

BAJ E

STAFF REPORT ENGOOI-Il

January 10, 2011

Page: 17

File: A19-2N

Pending #:

APPENDIX "C"

SUNNIDALE PARK RESERVOIR AND BOOSTER PUMPING STATION

COMMITMENTS STATUS

Sunnidale Park Master Plan

Section 4.4.1, specifically Table 1.0 Park Program

IDENTIFIED STATUS

REQUIREMENT

Locate Reservoir near

_____________________________________________________

Reservoir and Booster Pumping Station is located as per Park Master Plan with minor shift

Sunnidale Road which allows: saving of a large quality tree, saving of an additional 20 trees; allows the southeast corner of the reservoir to be approximately 300 mm lower.

Pump House to be designed for Although this is a unique building, a LEED certified Professional has prepared a report, provided

minimum LEED Silver

recommendations and continues to work to offer improvements to the design so that the

Booster Pumping Station can achieve the intent of LEED Silver.

Protect Existing trees (identified The City's Urban Forester will be reviewing the Landscape Architect's Tree Protection Drawings

as significant) and enhance that will be required as part of the Site Alteration Permit and the tender drawings. The

planting buffer along Sunnidale

Successful Contractor will be required to implement the approved tree protection plan and the

Road

City will monitor throughout construction and the Maintenance Period.

Fencing will be placed around tree stands and individual trees to minimize the potential for the

contractor to accidently damage the remaining trees

To increase the number of trees that are to be saved, sheet piling will be utilized so that gradual

slopes can be avoided which would require additional trees to be removed.

Prior to construction the City will implement selective specimen tree planting/management along

Sunnidale Road to assist in establishing buffering and screening of the construction activities

______________________________

and proposed Booster Pumping Station.

Buffered views from adjacent See notes above in regards to the Sunnidale Road buffering

residential areas and park areas

The Booster Pumping Station will be buffered from views from the north by berming and tree

plantings as per the Landscape Architect's Landscaping drawings, however there cannot be

trees on top of the reservoir. The view from the east will be obscured by low plantings and

______________________________

higher bush plantings since there cannot be trees located on top of the reservoir.

Maintenance access and The main maintenance access for the Booster Pumping Station will be located off the existing

parking (combine with other northerly access road to the existing facilities. It is anticipated that there will be one

functions of the Park as much as maintenance vehicle per day. The Booster Pumping Station access will be controlled to

possible) prevent other vehicles from accessing the building. Parking for City maintenance vehicles only

will be adjacent to the Booster Pumping Station.

A secondary emergency access to the Booster Pumping Station will be placed over the

proposed servicing corridor which will stretch from the Booster Pumping Station to the

Sunnidale Road Right-of-way. This access will be secured so that non-City vehicles will not be

able to access. It will also be softscaped with reinforced pathway with grass cover so that it will

not look like a vehicular access.

Secured access hatches to the reservoir that are required for Health and Safety reasons will

have the meandering pathway in close proximity to reduce the effects of vehicular traffic in the

park. There may be only one maintenance vehicle relating to the reservoir per month under

regular security checks.

Security lighting Continuous lighting of the overall facility will be minimized

The design of the security, morality and motion lighting will be reviewed as design progresses.

It is anticipated that there will be no highpole spread lighting in relation to the Booster Pumping

Station design.

Pump House to be 80m2 The proposed footprint of the Booster Pumping Station after design has been found to be larger

(861 ft2) in size than anticipated. This is further discussed in the Staff ReportThe City of

BA E

STAFF REPORT ENGOOI-Il

January 10, 2011

Page: 18

File: A19-2N

Pending #:

Main Trail - Granular trail with The City will be implementing the recommendations from the Parks Planning Section as to the

trail hardening to width of 3.0 width of the trail and the surface composition. The recommendations will be based on the trail

metres where required hierarchy as outlined in the Parks Master Plan

Trails will be barrier free and has The City will be implementing the recommendations from the Parks Planning Section as to

been configured to have slopes barrier free requirements for the trails that will be temporarily relocated due to the construction

less than 8% and the final trail layout in the vicinity of the newly constructed works.

It is proposed to meander the trail across the top of the buried reservoir so that the trail slopes

do not exceed 8%.

Seating along trails to be low As part of this design of the meandering pathway across the top of the reservoir, seating will be

maintenance and durable placed at locations to be approved by the City's Parks Planning Section. The City will also be

installing its typical park furniture with emphasis on low maintenance and durability

Arboretum - Trail connections Trail connections will be temporarily relocated in the vicinity of the construction to allow

between the Arboretum and continued use during construction. The final restoration of the area will have a meandering trail

other parts of the park on top of the buried reservoir that will connect the arboretum and the other public facilities within

the park.

ViewsNistas - Existing The location of the Booster Pumping Station and buried reservoir have maintained the existing

views/vistas in open space to be views/vistas in the open space area.

preserved

Views and vistas to be Location of the seating areas will be made in consultation with the Parks Planning Section

considered when locating

seating areas, trails and other

park additions

Open Space Area - Protect There will be no structures located on top of the reservoir so therefore the existing views/vistas

existing views/vistas are protected with the burying of the reservoir. The City of

BA E

STAFF REPORT ENGOOI-Il

January 10, 2011

Page: 19

File: A19-2N

Pending #:

SUNNIDALE PARK RESERVOIR AND BOOSTER PUMPING STATION

COMMITMENTS STATUS

Sunnidale Park Master Plan

Section 6.2, Specifically Table 2.0 Implementation Strategy

IDENTIFIED STRATEGY STATUS

B3 - Where possible above PowerStream (Hydro) has been notified of this strategy and will be replacing the existing poles

ground utilities shall not be with higher poles in approximately the same location. Bell follows PowerStream's lead since

located on the park side of they use the same poles.

Sunnidale Road

B4 - The reservoir, pumphouse Discussed in the main body of this Staff Report. In summary, further detailed reviews and

and access road be survey of the site have concluded that by shifting the reservoir 10 metres to the west that we

positioned in Sunnidale can save an additional 20 trees including several significantly sized healthy trees and are able

Park in the location to lower the north- east corner of the grading approximately 300mm, while still keeping the view

identified in the Master shed intact.

Plan

B5 - Any above ground The Booster Pumping Station height has been reduced as much as practical and we have

infrastructure that is to provided enhanced landscaping surrounding the building to reduce the hard edges. The access

installed as part of the hatches for the reservoir that are needed for Health And Safety reasons have been incorporated

reservoir construction be into the landscaping clusters and meandering pathway. There will be no communications

installed to minimize impact towers as part of this project

on the_park

B7 - Final Detail Design

____________________________________________________________________________________

The design is being presented to Council via Staff Report ENGO25-10.

drawings for the reservoir

be presented to Council for

endorsement

Dl - Archaeological A Stage 2 Archaeological Assessment has been undertaken where the construction is planned

Assessment - Stage 2 and the report has been registered with the Ministry of Culture.

where construction is

planned

E2 - Tree Enhancement

_________________________________________________________________________________________

The landscaping plan will include the placement of additional trees at the Sunnidale Road RightPlanting (Reservoir) of-way, infilling and cluster planting to provide screening at key locations. The drawings will be

endorsed by Parks Planning and the City's Urban Forester. Note that we are unable to plant

trees on top of the reservoir.

E4 - Inventory of trees on the Parks Planning and the City's urban Forester have undertaken a tree inventory. The

table lands adjacent to information was used to determine the finalized placement of the reservoir and Booster

Sunnidale Road Pumping Station to save an additional 20 trees.The City of

BAPJ E

STAFF REPORT ENGOOI-Il

January 10, 2011

APPENDIX "D"

Page: 20

File: A19-2N

Pending #:

__________________

REQUIRED APPROVALS

________________________ REQUIREMENT

__________________

STATUS I ACTION

APPROVAL AGENCIES

_____________________

Ministry of the Environment Drinking Water Works

_____________________

To be submitted as part of the

(MOE) Amendment for a new Reservoir MOE/City's amendment process

_____________________________

and Booster Pumping Station prior to construction

Ministry of the Environment Certificate of Air Approval for the To be submitted after tender

(MOE) Standby-Generator & Chlorine award once Stand-by Generator

_____________________________ Room manufacturer has been selected

Lake Simcoe Region Notification only since project is Submission made, Confirmation

Conservation Authority (LSRCA)

outside Zone of Interest Meeting Nov 25.

-No further requirements

Department of Fisheries and No harmful alteration, disruption LSRCA determined there will be

Oceans (DFO) or destruction (HADD) no HADD.

____________________________

requirement - No further requirements

Ministry of Natural Resources No cut/fill operations in a Notification to be completed just

(MNR)

floodplain, there no permit prior to construction

______________________________

required. Notification Only. commencement

Ministry of Culture Archaeological Report - Stage 1 Included Archaeological Report

and 2 registered recommendations in Tender

documents regarding if further

findings are found.

- No further approval

_____________________________ _____________________________

requirements

First Nations Notification only -Provided registered

Archaeological Report.

-No further requirements

Migratory Bird Act Ornithologist to review site and City to retain Ornithologist prior

Sign-off prior to tree cutting to to construction commencement

ensure that no fledglings will lose

________________________________

their nests

Ministry of Labour (MOL) Notice of Project to be issued to

________________________________

Successful Contractor to provide

confirm MOL is aware of project prior to construction and post

________________________________ ________________________________

in site trailer

Occupational Health & Safety Act Prepare Pre-start Health and To be done by independent third

(also City requirement) Safety report party as construction nears

_____________________________ _____________________________

completion

Technical Standards and Safety Various equipment requirements TSSA requirements to be

Association (TSSA) addressed by Successful

_____________________________ _____________________________ Contractor during construction

Electrical Safety Authority (ESA) Various equipment requirements ESA requirements to be

addressed by Successful

_____________________________ _____________________________ Contractor during construction

UTILITIES

PowerStream (Site) Site Servicing Agreement (md. To be obtained prior to

Transformer) construction

PowerStream (Right-of-Way) -Cost Sharing Agreement - Agreement to entered into prior

-Municipal Consent to construction

-PowerStream to obtain

Municipal Consent prior to their

_____________________________ _____________________________

poleline construction The City of

BA E

STAFF REPORT ENGOOI-Il

January 10, 2011

Page: 21

File: A19-2N

Pending #:

Enbridge Gas Servicing Agreement - Successful Contractor obtains

_____________________________ _____________________________

approval during construction

Bell Canada Servicing Agreement Phone lines to be ordered by

City's ICT Department during

_____________________________ construction

Rogers

_____________________________

Servicing Agreement Not required

Communications A communications tower is No further approval

required therefore no permit requirements

______________________________

required

CITY APPROVALS

______________________________

Site Alteration Permit Permit required to ensure To be obtained prior to

Developer (in this case the City) construction. Submitted and

is aware of the local by-law currently under review

requirements for sedimentation

______________________________

protection and tree protection

Tree Cutting Permit Permit required to ensure

______________________________

To be obtained prior to

Developer (in this case the City) construction. Submitted and

is aware of the local by-law currently under review

________________________________

requirements for tree cutting

Building Permit (includes Building Permit required

________________________________

To be obtained prior to

Plumbing and Fire Sign-off) construction. To be submitted

subsequent to Council

______________________________ ______________________________

endorsement of the Detail Design

Site Plan process (Planning, A Site Plan agreement is not To be obtained prior to

Engineering, Parks Planning)

required however the process will construction. To be submitted

be followed to ensure proper subsequent to Council

______________________________

public notification of project endorsement of the Detail Design

Zoning To be in compliance with current Deemed to be compliant by

zoning requirements Zoning Branch.

_____________________________ _____________________________ No further action

Sunnidale Park Master Plan Consultation Completed November 17, 2010.

Consultation Group

Energy and Water Conservation Endorsement required Endorsement to be obtained

Officer prior to tender. Submitted and

________________________________ ________________________________

currently under review

Urban Forester - Endorsement required Endorsement to be obtained

- Monitoring during construction prior to tender and ongoing

- Monitoring after construction through construction and

subsequent to construction.

Submitted and currently under

______________________________ ______________________________

review

Park Programming Notification required To be notified prior to

_____________________________ _____________________________

construction.

Legal Transformer Easement To be obtained prior to

_____________________________ _____________________________

construction completion.The Gity of

BAJ E

STAFF REPORT ENGOOI-Il

January 10, 2011

Page: 22

File: A19-2N

Pending #:

APPENDIX "E"

SUNNIDALE PARK RESERVOIR AND BOOSTER PUMPING STATION

COMMITMENTS STATUS

Class Environmental Assessment Schedule "B"

Proposed Zone 2 North System Improvements

IDENTIFIED ACTIONABLE ISSUE STATUS

Prepare a Park Master Plan for Sunnidale Park to ensure that the Completed. Endorsed by Council per Motion 09-G-262

proposed reservoir and pump house are located in the best

location in consideration of the existing and future uses of the

Park.

Provides redundancy to Zone 2N and increases system security to Fulfilled once Sunnidale Road and Booster Pumping Station are

meet emergency, fire fighting, and existing and future water needs. operational

Visual impact of the reservoir is minimized as the reservoir is The detailed survey has shown that the north east corner of the

generally below existing grade.

reservoir will be approximately 4-5 feet above existing grade

including topsoil and grassed cover while previous indications have

noted it to be 6-8 feet.

Proposed reservoir to be buried and unfenced. Area will still be As per the preliminary design, the reservoir will be below grade and

available as open space. unfenced so that the area will remain as Open Space

Minimizes impact on open space areas. As shown in the preliminary design, the open spaces have been

preserved The City of

BAJ E

STAFF REPORT ENGOOI -11

Page: 23

January 10, 2011

FIe: A19-2N

Pending #:

APPENDIX "F"

7

The city of

BA-B3 E

6

EXTERIOR COLOUR SCHEDULE

I NATUGALEIELD STORE

2ARCROECTSRUL SEC 1110CR COURSE NUTURUL GREY COLOUR

SAA00000RLUAIRUl2(MECRUNIOULLOJURES)

4 rECOLOR 010000-ICE OBEY OOLOUR

I GEIIIIEORE-000EIE4ISHE00000000R0 -1451082111112511

S IIAIZIP REEL 110 50 CR1000 MElEE EEOC IRS S 051CM 1)0 1145 OR EL IC

I 0000IJ,ARELAREO 1100)45- RAIOEAI5ROCO 011255

I E0450IRGEOAE ROAR 0001105 E012121.5S:N0000RER 051011

RRRRLIORI2E)SL DOORS: DII UI D1-OR-EEUTRER RUE)

REORIIMO2 UAT0001 FORGES CLEAR 4)45010000110011150501

STRUCDLROL 400141 LROI.OAG 024141110 10 MUTER 0001151

INTERIOR COLOUR SCHEDULE

IS 021141- RE'S ' 5*4,0110 MIC4RR0005TS

I REEL bLUe, *51 I CO 485050 1) 05,0)541

12 E OUR 110CR-S TACOS 11014 SUER IS

10 11 12

COLOUR SCHEDULE OCT06-2010

SUNNIDALE PARK RESERVOIR'4

i

1

j

II

i

!

i

r

p

r

:

I i

t?l

"

1

,

1:

1

I - 4'.

Lj

[iJ

(I)

-I

ii

-n

m

0

-CD

CD (

CD

>Ir.)

F',)

z UNDERGROUND (BURIED)

Q------------ j---- RESERVOlR925mx385m -----------------------------3O3' x126')

iF--'---H

----------------------------- --------------------CHLORINE STORAGE AREA

- for disinfecting water

-4

ti

II III

L

CHLORINE SCRUBBER

- to prevent chlorine gas from

leaking to environment

--STAND-BY GENERATOR

71m [5]

- to sustain water supply

\

(by pumping) during hydro

\

power outage

SIZE OF THE PROPOSED PUMP HOUSE

17.lm x 8.8m (56' x 29')

4

ii

-ii

m

0

C)

0'

-tJ-n-tJ

CD

CD C2

CD

5.> ;:.,

01

zThe Curve Roof (Option A)

or High Flat Roof (Option B)

to accommodate roof top

equipments.

The building height is to

accommodate the

Gbber

____ IlllfT

i w w w w U

STORAGE

AREA

SCRUBBER

PUMP ROOM

I

0

k I

-______

GENERATOR

H

I

The building height is to

accommodate the

Stand-by Generator

I

I4

Lu

Cl)

-Ii

ii

m

0

C,

CD = A)

CD (

CD

0)

z LEGEND

SEATiNG PEA

:

,

,Hsi.

--1'

Si

H- I S

S

- S

- 5_ 5

iS S S

S

/

SS

- S

H5 .5 \i. L

N

//

S

/

S

/

55 S\

/5

)/,_•

575

VEITIFY DEVISE

8UNNIDALERE8ERVOIRANDP8.

___________________________________________ 5575755 y

0.7.

2557 GENERAL SITE $JJ

OVOSSIS II

5575

0.?.

ISOS SSSITS 505555

COl

557555757 ussr sirs 55555755 5000510s5tY.

5' 1

5kJ

C,,

-I

-n

-n

m

0

cU

A,

G)

0'

um

CD 5)

Q" CD

(c2 z

LANDSCAPE / CRADINC

CONCEPTThe city of

BAPJ E

STAFF REPORT ENGOOI-Il

January 10, 2011

Page: 28

Fite: A19-2N

Pending #:

APPENDIX "G" SURVEY RESULTS AND CITY RESPONSES

Which of the concepts do you prefer? City Response;

(57 Responses, 86% in favour of curved Roof)

Curved Roof - If it had to be one height, would prefer option 1 with the

curved roof.

No further comment

Designers have investigated numerous ways to

Curved Roof -They are all very large. Less would be more.

reduce building floor area and height however,

need to provide for minimum equipment and

________________________________________________________________

Health & Safety requirements.

The remaining tall trees at the west of the site are

Curved Roof - Solar panels Incorporated? shading the Booster Pump Station which is not

conducive to solar panels use.

Curved Roof The curved roof designs helps integrate the building with the

current pavilion.

No further comment

Curved Roof - The curved roof seems more organic, and seems to let the

most light through the structure.

No further comment

Curved Roof - Did they all have to be so ugly?

Based on the results of the public survey, 86%

are in favour of the curved roof design.

Access treatments have been designed based on

Curved Roof - Minimize impervious surfaces where possible. Take

recommendations from the City's Parks Planning

opportunity with landscaping to demonstrate native plants. Branch. Asphalt will be provided for accesses

that require daily Operations use.

Curved Roof - Siding should not be wood after the stone foundation. A

Material selection has been reviewed with the

slate/stone (not plaster) would be more natural to the area.

architect and the City's Facilities Staff with

respect to vandalism and durability.

Curved Roof - Great engineering design, simple to view and understanding;

pleased.

No further comment

There will be no resurfacing and curbing of

Sunnidale Road as part of the reservoir and

Curved Roof - Upon road resurfacing of Sunnidale will curbs be added? Booster Pump Station project. The comment has

been provided to the Engineering Department's

____________________________________________________________________ Design & Construction Branch.

The reservoir level Reservoir will be completely

below grade. Any protrusions will be covered and

Curved Roof - I would encourage you to lower the water storage tank addressed in landscaping. The minor shift in the

another 4 or 5 feet so there is no evidence of it below ground reservoir location from the Sunnidale Park Master

Plan has allowed the reservoir protrusion to be

________________________________________________________________

reduced.

The building designers have worked with

Engineering and Operations to minimize the

Flat Roof - Pump house is larger than suggested. Safe removal of wildlife in

building's footprint. It is larger than original due to

the area of deforestation addressed?

safety considerations.

Wildlife relocation and protection of nests will be

________________________________________________________________ addressed prior to tree removal.

Curved Roof - Much thought has gone into the whole plan, keeping the

No further comment

integrity of the park

The immediate construction area of the Park will

Curved Roof - I hope there will be no restriction to public use of park before be fenced for public safety during construction.

or during construction. However, the majority of park open space and all

the northern trail will not be affected.

The most suitable location has been determined

Neither - I think the park is a poor location for this project.

through the Class EA process and the Sunnidale

___________________________________________________________________ Park Master Plan process The City of

BAJ E

STAFF REPORT ENGOOI-Il

Page: 29

January 10, 2011

File: A19-2N

Pending #:

Do you agree with the use of natural building materials? City Response;

(47 Respond yes 98%, 1 Responds No 2%.)

Yes - Care needs to be taken with colour and design. Incorporate Natural

area colours (Tree trunks - barn board. Foundation Stone could look like an

old barn, or perhaps river rock)

No - Stone and galls okay, but wood will be susceptible to vandalism (fire,

graffiti, carvings, etc)

Building materials and colours have been

addressed with the architect

Yes - Lower portion of wood. Should be more of a slate stone.

Yes - Natural is always better, conducive to the area.

Yes - But not too much glass because of vandalism.

(46 Respond Yes 96%, 2 Respond No 4%)

Yes - Everything possible to make the building disappear - colour, materials,

Building materials and colours have been

size and form that blends in with the existing environment,

addressed with the architect

Some trees will have to be removed, however,

the area of removals is largely unhealthy trees.

Yes - I am more concerned that trees are not removed. The latest design has shifted the reservoir

location and we have saved an additional 20

____________________________________________________________

trees and a 500 mm diameter White Pine.

Yes - Plant trees to hide it.

___________________________________________________________________ Buffering with trees has been strategically placed,

Yes - Plant trees completely around the eye sore.

however, trees cannot be placed on top of the

Do you agree that the appropriate level of architecture has been included in

City Response;

the design?

I

(34 Respond Yes 79%, 9 Respond No 21%)

Building size has been reduced to bare minimums

No - Make as small as possible.

while maintaining equipment and worker

____________________________________________________________________

clearances

Building materials and colours are natural

No - Prefer a natural looking building

including stone and wood

Yes - Concrete should be coloured prior to use to reduce future

maintenance

Exterior concrete will not be used.

No - Why painted concrete and not coloured? Future maintenance would be

easier.

Exterior concrete will not be used.

No - A more pleasing design would be better.

86% of respondents are in favour of architectural

design.

Yes - Ugly is ugly.

No - not painted block.

There will be no painted block for the exterior

Building materials and colours are natural

Yes - As natural as possible to blend in with surroundings.

including stone and wood

Yes - I agree with current proposal-natural building materials. No further comment

90% of respondents are satisfied with the level of

Uncertain. Haven't received enough information to see evolution of the

information provided. Design information was on

design.

City website since June 29 Open HouseThe City of

BA E

STAFF REPORT ENGOOI-Il

Page: 30

January 10, 2011

File: A19-2N

Pending #:

Do you agree that we have kept the view shed intact?

City Response:

(35 Respond Yes 83%, 7 Respond No 17%)

Yes - Good compromise between keeping the forest cover and maintaining

the view shed.

No further comment

Yes - The plan seems to keep it intact, minimizing impact on the park. No further comment

Yes - Provided trees are not removed, the view is secondary to this

___________________________________________________________________

The location of the reservoir and Booster

Pumping Station were determined in the

Sunnidale Park Master Plan

No - More trees are needed to hide the structure.

Taller shrubbery has been added to landscaping

No - A circular roof will hide it.

A circular roof cannot be placed on the reservoir

Not Sure - Difficult to envision sight lines from diagrams/drawings.

Air photo is available on the project website

Yes - Mostly. Hopefully no chain link fence with barbed wire.

No chain-link fence is incorporated into the design

(43 Respond Yes 90%, 5 Respond No 10%)

With 86% favouring a curved roof and 90%

Yes - I think that the pumping station needs at least one more design.

satisfied with the information provided, there will

___________________________________________________________________ _

likely not be any further major changes

No -Would appreciate a more comprehensive brochure about the project.

90 % were satisfied with the information provided.

Information can be found on the City's website

Yes - Please ensure that the off leash dog walking park remains intact. Off leash area is outside project zone

Yes - It would be good if you would design a building which is less visible.

Planting will be used to reduce building view.

Blends in better with the background and park.

Building materials and colours have been

addressed with the architect

Yes - Dislike appearance and did it need to be so tall.

Building was designed to meet minimum

equipment & worker clearances

Yes - Doesn't belong in the park, City should preserve the park that was

Location and need were addressed during the

given to them.

Class EA and Master Plan process

Public input opportunity was provided during the

Class EA and Park Master Plan process and

No - Its already a go, I don't feel like I have any input.

Open House. Several suggestions have been

____________________________________________ incorporated into the desiqn.

Yes - Very helpful.

________________________________________________________________ No further comment

- The City of

BA E

STAFF REPORT ENGOOI-Il

January 10, 2011

Page: 31

File: A19-2N

Pending #:

Miscellaneous Comments

City Response;

Building designed to meet minimum equipment &

worker clearances. Operator preference is

Reduce overall height, there doesn't seem to be the need for the building to

permanent crane due to Health and Safety

stand so tall as it currently is designed. A permanent overhead rail for

reasons. 86% of respondents are satisfied with

moving pumps was mentioned, is there an Option to use a portable system.

level of detail and architectural effort put into the

Prefer the location on the master plan. The pumping building should

building. The building height has been

disappear and not be noticed,

determined by the height of equipment and

maintenance requirements. The equipment

cannot be placed below ground so as to minimize

____________________________________________________________________ damage due to potential flooding.

The most critical issue about the reservoir location, from the point of view of

the BFNC, is the great number of trees to be removed to allow for the actual

A balance between locating the facility within the

reservoir structure and the ten metre wide construction buffer around it, as

park and minimizing tree removal was achieved

well as the access roads. The original proposal shows the removal of 148

,

during the EA and Park Master Plan process.

trees and the alternative layout to increase tree preservation still removes

128 trees (of which 5 are considered poor health/dead)